S-34.1, r. 1 - Regulation respecting petroleum exploration, production and storage in a body of water

Full text
74. The authorization holder must ensure that the measurements of the stratigraphic survey path deviation are taken at intervals that allow the position of the wellbore to be determined accurately and that do not exceed 150 m, unless there is a wellbore stability problem.
O.C. 1251-2018, s. 74.
In force: 2018-09-20
74. The authorization holder must ensure that the measurements of the stratigraphic survey path deviation are taken at intervals that allow the position of the wellbore to be determined accurately and that do not exceed 150 m, unless there is a wellbore stability problem.
O.C. 1251-2018, s. 74.